Zerah’s Farm

Rhône Valley Varietals

Building exterior finished

Building exterior finished

At Zerah’s Farm, we dedicated our July 4th weekend to meeting another milestone with our vineyard building. We meticulously painted the single hung windows and installed exterior lights, making sure they complemented our Victorian-themed building flawlessly. The...
New carriage house doors

New carriage house doors

At our vineyard, we wanted to capture the timeless elegance of the Victorian era. That’s why we enlisted the help of a skilled blacksmith in Pennsylvania to craft custom carriage door hinges, adding an authentic touch to the building. You’ll notice the...
Deer herd visiting

Deer herd visiting

Black-tailed deer are frequent visitors to our property. Since we have yet to fully enclose it with deer fencing, they roam freely in the area. In the distance, the enclosed vineyard building awaits the completion of its windows, siding, and roof shingles. We’ve...
Building almost closed in

Building almost closed in

Within a month, Alta Vista Construction has nearly completed enclosing the building. Luckily, the weather has been on our side, allowing us to make great progress. You can now see the roof scissor trusses, with just the final roofing left to be...
More tanks and solar

More tanks and solar

We are thrilled to announce the addition of a new 5000-gallon water storage tank for irrigating Block C, perfectly complementing the existing 10,000-gallon water storage tanks nestled by the majestic oak grove. Furthermore, we have recently installed a...
Framing the vineyard building

Framing the vineyard building

We have discovered an exceptional general contractor to handle the construction of our magnificent vineyard building. Roger Moore, from Alta Vista Construction in Santa Rosa, CA, has taken charge of framing the exterior shell of the building with utmost precision and...
High tech septic

High tech septic

A new septic system has been installed. The original septic field, which was pre-approved when we purchased the property, posed a challenge as it was situated right in the middle of our vineyard planting area. But thanks to our state-of-the-art septic system, we were...
Pull, push, pull…

Pull, push, pull…

When an electrical contractor’s bid exceeds $250,000 to extend wiring from your electrical panel to the future building envelope, it’s time to think beyond the conventional. Perhaps a quick visit to YouTube for some creative ideas? You’ll need thick...
Foundation completed!

Foundation completed!

Welcome to our brand new space! Take a moment to admire the freshly poured floor slab, revealing its smooth and pristine surface. If you have a keen eye, you’ll notice two strategically placed floor drains, a testament to our commitment to cleanliness. The grade...
Starting the vineyard building

Starting the vineyard building

Embarking on our next endeavor, we proudly announce the commencement of a remarkable project – the construction of a brand-new vineyard building. This structure will serve as a haven for our state-of-the-art equipment and feature a meticulously crafted wine...